Section Kurilo - Rebrovo
Contractor: Consortium "Railway 2012-2016" - Vodstroy AD
Executor: Infrastructure Construction Ltd.
Date of Contract: August 3, 2015
Date of Final Acceptance: December 9, 2016
Project Description
Restoration of Design Speed in the Section Kurilo - Rebrovo, Track No. 2 from km 13+294 to km 23+632 with a length of 10,338 m, including adjacent stations: Kurilo Station - TP 2 with a length of 980 m and adjacent turnouts No. 8, 10, 14, 9, and 3; between turnouts No. 10 and No. 14 with a length of 46 m, as well as between turnouts No. 3 and No. 9 with a length of 22 m, and Rebrovo Station - TP 2 with a length of 891 m and adjacent turnouts No. 1-2
Construction: 2nd group, 1st category
Complete excavation of the ballast prism and sub-ballast carpet in the section and removal to the depot; Compaction and reinforcement of the earth subgrade/recycling of subgrade materials;
Demolition of existing railway track type 49, complete dismantling and packing, and installation of railway track type 60 on a platform with ST-6 sleepers, elastic resilient fastening at a rate of 1800 pcs/km for BRP; Construction of first, second, and third leveling, ballastless track, including ATZ units and neutralization of voltages in BRP;
Repair and rehabilitation of watercourses;
Supply and installation of reinforced concrete ducts type ECT 200/30 and ECT 200/50;
Repair, rehabilitation, and replacement of waterproofing on reinforced concrete bridges; Restoration of anti-corrosion coating on steel structures; Supply and installation of lead plates with a thickness of 16 mm (2x8mm) Pb99.94 on steel bridges;
Construction of Romcha village platform; Construction of Vlado Trichkov village platform;